FAQCategory: SchedulingWhen modifying baseline work field into the variance table does not sum to summary task. All summary totals must be recomputed manually.

When modifying baseline work field into the variance table does not sum to summary task. All summary totals must be recomputed manually.

1 Answers

The changes made to the baseline fields do not cause the project to be recalculated.

After you set a baseline, you can still edit baseline values. However, edited baseline values do not cause any recalculation of baseline work fields.

The best approach to using the Baseline Work field, would be to make the desired changes to the Work field then set a baseline.