When should I use Task Sheet?
1 Answers
Use the Task Sheet view to:
- View a list of tasks and task information quickly when you don’t need to see the information graphically over time.
- Review progress by comparing planned (baseline) dates and actual start and finish dates, and by checking the progress of each task.
- Establish sequential task dependencies by linking tasks. When you link tasks, you can see how a change in the duration of one task affects the start and finish dates of other tasks, as well as the project finish date.
- Assign personnel and other resources to tasks.