When should I use the “Split Task” functionality?
1 Answers
Use the “Split Task” functionality in the situation where the work for a task in your project needs to start, then stop somewhere in the middle of the task, and then resume at a later date.
In this way, Project Plan 365 gives you the possibility to account for interrupted work, when an issue arises that causes a non-work period delay in the schedule. This allows for the individual task duration to remain the same, while potentially extending the duration of the project.