FAQCategory: TasksWhy doesn’t a milestone has a duration of 0 days?

Why doesn’t a milestone has a duration of 0 days?

1 Answers

The milestones can also have a duration rather than 0 days and can be marked as milestones by selecting the tasks and going to the Task Information dialog – Advanced tab and checking the “Mark task as milestone” checkbox. Only if you do not need to allocate time for your Milestone you can set the tasks Duration to 0.