How do I add costs?
1 Answers
To set the costs for resources, go to Resource Sheet view and set the standard rate for each resource. To add a cost for a specific task, set in Resource Sheet view resources of type cost and then assign the cost for each task in Task Information dialog. Another option to set the cost for a task is to edit the Cost field in Gantt Char view.