By copying a resource the following information about it will be copied: resource name, type, material label, initials, group, std. rate, cost/use, base calendar and code.
To copy a resource click Copy option from Task tab, press CTRL+C/Command+C or select Copy Resource from contextual menu after you right click on a task.
In order to paste a resource, select the rows where you want to paste the selection and Click Paste.
Question Link
Question Link
Question Link
Question Link
Question Link
Question Link
Question Link
Question Link
Question Link
Question Link
Question Link
Question Link
Question Link
Question Link
The difference between fixed units and fixed duration can be seen when modifying the units and work for a task. For Fixed units tasks, when revising units and work -duration is recalculated. For fixed duration tasks, when revising units - work is recalculated and when revising work-units are recalculated.
Question Link
Question Link
Question Link
To see the Task Mode field, use Insert column option under Format menu and select in the Field Name: Task Mode.
You can insert and display this column in views like Gant Chart, Tracking Gant or Task Sheet view.
Task Mode column displays an icon indicating whether a task, is a manually scheduled task, or an automatically scheduled task.