FAQ Project Plan 365

Browse by Category

What is Fixed Duration Task Type?
Question Link
Answer
Fixed Duration Task Type applies to a task in which the duration is a fixed value and any changes to the work or the assigned units (that is, resources) don't affect the task's duration.
What is Fixed Work Task type?
Question Link
Answer
Fixed Work Task Type applies to a task in which the amount of work is a fixed value and any changes to the task's duration or the number of assigned units (or resources) do not affect the task's work.
What is Fixed Units Task Type?
Question Link
Answer
Fixed Units Task Type applies to a task in which the assigned units (or resources) is a fixed value and any changes to the amount of work or the task's duration do not affect the task's units.
What does the “Set Task Type” functionality do?
Question Link
Answer
The “Set Task Type” functionality, as the name indicates, allows you to change the types of automatically-scheduled tasks. The available task types are: fixed units, fixed work, and fixed duration. Project looks at a task's type to determine how duration, work, and units will behave as Project schedules your project.
How to change the Task Mode for a task?
Question Link
Answer
To change the Task Mode, click in the Task Mode field. In the list that appears, click Manually Scheduled or Auto Scheduled. You can also select specific tasks, then in the Task Information dialog under Task menu, General tab, in the Schedule Mode group, select Manually Scheduled or Auto Scheduled and click OK.
What are manually scheduled tasks?
Question Link
Answer
Manual tasks are tasks with task mode manually scheduled.  They should be used when you want to explicitly set a task's start and finish dates and not allow it to be changed automatically by the scheduler based on changes to other tasks. When a task is in manually scheduled mode, the Start, Finish, and Duration columns can be blank or include text values in addition to recognizable dates.
What are automatically scheduled tasks?
Question Link
Answer
Automatically Scheduled tasks have Start, Finish and Duration values calculated by Planner based on dependencies, constraints, calendars, and other factors.
What does the “Set Task Mode” functionality do?
Question Link
Answer
The “Set Task Mode” functionality gives you the option of deciding how much control you want over task scheduling in a project. The Task Mode field indicates whether a task is scheduled manually or automatically scheduled. By default, tasks are set as auto scheduled, with a start date, finish date, and duration calculated based on inserted fields values.
How to enter a material resource in Resource Sheet view?
Question Link
Answer
To enter a material resource in Resource Sheet view, in the Type field, click Material. In the Material Label field, enter the label (for example, yards, tons, or boxes) for the resource.
How do I set start finish date hours?
Question Link
Answer
Before starting to schedule your project by setting start and finish dates, you can use the Date Format option on the File menu in the Options dialog box to specify the date format used to display information in date fields. For a task you can enter the time and the date in any order or you can use calendar picker to select desired date and hour.
What does the "Set start finish date hours" functionality do?
Question Link
Answer
The “Set Start Finish date hours” functionality, as the name describes it, allows you to set the start and the finish date hours to your tasks.
How do I change task scheduling options defaults for days, weeks, and months?
Question Link
Answer
To change task scheduling options defaults for days, weeks, and months click File – Options – Schedule tab – select the desired settings from the Hours per day, Hours per week, and Days per month boxes – click OK.
What does the “Change task scheduling options defaults for days, weeks, and months?” functionality do?
Question Link
Answer
The “Change task scheduling options defaults for days, weeks, and months” functionality, as the name describes it, allows to make changes in the tasks scheduling settings to indicate how much time you want to constitute a day, a week, and a month when entering and reviewing durations in a task view. It can also help you synchronize task scheduling with what you've established in the working time calendars for resource.
How do I exit the full screen mode?
Question Link
Answer
To exit the full screen mode, click on the Exit Full Screen Mode button from top bar or the Escape key.
How do I change the font settings for all the tasks or for a particular type?
Question Link
Answer
To change the font settings for all the tasks or for a particular type from your project, in the Format menu select Text Style. Apply the desired settings and click OK. The Text Style options will not override the ones made previously on tasks in the Font settings.
How do I delete a task from my project?
Question Link
Answer
To delete a task from your project, on the View menu click Gantt Chart – select the row corresponding to the desired task – click on Delete option under Task menu.
Does deleting a task affect the project schedule?
Question Link
Answer
Deleting a task from your project may affect your schedule and you may run into problems. If you have started tracking actual work for your project, don't remove tasks that have actual work or other tracking data associated with them, or you'll lose valuable historical project information. If you delete a summary task, either being collapsed or expanded, all of its subtasks are also deleted. After you delete a task, the application automatically renumbers the remaining tasks.
Does deleting a resource affect the project schedule?
Question Link
Answer
Deleting a resource from your project may affect your schedule and you may run into problems. The resource assignments involving a resource are also removed from the tasks in your project: deleting a resource means any assignments you’ve made are gone as well, such that you run the risk of orphaning tasks without anyone to perform them. Costs could change: when you remove a resource from a task, the application deletes any actual costs associated with the resource
How do I add text to a type of bars in Gantt Chart?
Question Link
Answer
To add text to certain types of Gantt bars, apply the Gantt Chart View – make sure you are not selecting any particular task or bar – on the Format tab, click Bar Styles- select the type of Gantt bar – click Text tab – select the desired text – click OK.
How do I change the color, shape, or pattern of Gantt bars?
Question Link
Answer
To change the appearance of Gantt bars for the whole project, apply the Gantt Chart View – make sure you are not selecting any particular task – on the Format tab, click Bar Styles – modify the pattern as desired and click OK.
What does the “Bar Styles” functionality do?
Question Link
Answer
By using the Bar Styles functionality, you can make view-wide changes to all the bars in the Gantt Chart view, which is different from the Bar option, that applies format changes only to the specific line item you've selected.
What is the difference between Assignment and Time Phased Assignment Fields?
Question Link
Answer
Assignment fields show information for each assignment. Assignment fields can be displayed in the sheet portion of the Task Usage and Resource Usage views Time Phased assignment fields show information for each assignment as distributed over its duration. Time Phased assignment fields can be displayed in the time phased portion of the Resource Usage and Task Usage Views.
What is the difference between Resource and Time Phased Resource Fields?
Question Link
Answer
Resource fields show information for each resource, including summarized information on all tasks assigned to each resource. Resource fields can be displayed in the resource views such as the Resource Sheet and Resource Usage views. Time Phased resource fields show information for each resource as distributed over the duration of resource availability on the project. Time Phased Resource fields can be displayed in the time phased portion of the Resource Usage View.
What is the difference between Task and Timephased Task Fields?
Question Link
Answer
Task fields show task-related information and can be displayed in the task views such as the Gantt Chart, Task Sheet, and Network Diagram views. Time Phased task fields show information for each task as distributed over its duration. Time Phased task fields can be displayed in the Time Phased portion of the Task Usage View.
How can I see the Total Slack field for my tasks?
Question Link
Answer
To see the Total Slack field for your tasks, click on the Project menu – Table – Schedule or insert the Total Slack column to the current table by clicking Format – Insert Column – select the Total Slack field – click OK.
Contact
Chat