FAQ Project Plan 365
Browse by Category
What happens if I edit the work amount of a fixed units task?
What happens if I edit the work amount of a fixed units task?
Question Link
Question Link
What happens if I edit the work amount of a fixed work task?
What happens if I edit the work amount of a fixed work task?
Question Link
Question Link
What happens if I edit the work amount of a fixed duration task?
What happens if I edit the work amount of a fixed duration task?
Question Link
Question Link
What is the difference between task types and task constraints?
What is the difference between task types and task constraints?
Question Link
Question Link
Why am I not able to change the task type of a summary task?
Why am I not able to change the task type of a summary task?
Question Link
Question Link
How can I make all tasks manually in my new project?
How can I make all tasks manually in my new project?
Question Link
Question Link
Can tasks be anything else but manually or automatically scheduled?
Can tasks be anything else but manually or automatically scheduled?
Question Link
Question Link
When should I use manual tasks?
When should I use manual tasks?
Question Link
Question Link
How to change a task from manual to auto?
How to change a task from manual to auto?
Question Link
Question Link
Why do some of my tasks have the finish and start dates blank?
Why do some of my tasks have the finish and start dates blank?
Question Link
Question Link
Answer
Go to Format menu and click on Insert Column. Select in the Field Name - Task Mode. If you already have the task mode column skip the previous step. If the Task mode is manual change it to Auto. When tasks are Automatically scheduled, the Planner calculates the Start, Finish and Duration values.
Why is my manual task set to Fixed Duration?
Why is my manual task set to Fixed Duration?
Question Link
Question Link
How to change the bar color for manual tasks?
How to change the bar color for manual tasks?
Question Link
Question Link
Is it possible to delete multiple tasks?
Is it possible to delete multiple tasks?
Question Link
Question Link
Answer
You can delete multiple tasks by selecting multiple consecutive rows using either CTRL or SHIFT keys on you keyboard and then click on Delete option from the Task menu, or press on Delete key or use the Delete Task option from the contextual menu to delete multiple tasks at a time. The IDs of the remaining tasks will be automatically renumbered.
Is it possible to insert more than one task at a time?
Is it possible to insert more than one task at a time?
Question Link
Question Link
Answer
To insert multiple tasks, select multiple consecutive rows using either CTRL or SHIFT keys on your keyboard and then click on Insert option from the Task menu, or press on Insert key or use the New Task option from the contextual menu to insert multiple tasks at a time. These tasks will be positioned above the selected rows in the tasks list. The number of newly inserted tasks will be equal to the number of selected rows.
Is it possible to insert a task between two tasks?
Is it possible to insert a task between two tasks?
Question Link
Question Link
When should I create a recurring task?
When should I create a recurring task?
Question Link
Question Link
How can I move a task? It keeps the start date and duration as priority, rather then logic links I am giving with predecessors.
How can I move a task? It keeps the start date and duration as priority, rather then logic links I am giving with predecessors.
Question Link
Question Link
Answer
If a task has any actuals applied, such as an actual start date or a percentage of work completed, the task can't be rescheduled any earlier than the date when the task actually began. If no progress is entered and the task has an inflexible constraint, the constraint can take precedence over task dependencies. Please remove % complete values then try again to change predecessors value.
What role do Constraints have?
What role do Constraints have?
Question Link
Question Link
How does the flexible constraints affect tasks?
How does the flexible constraints affect tasks?
Question Link
Question Link
When should I use semi-flexible constraints?
When should I use semi-flexible constraints?
Question Link
Question Link
When should I use inflexible constraints ?
When should I use inflexible constraints ?
Question Link
Question Link
How do I make my project as flexible as possible ?
How do I make my project as flexible as possible ?
Question Link
Question Link
Where do I see the constraint type of a task?
Where do I see the constraint type of a task?
Question Link
Question Link
What does ALAP mean?
What does ALAP mean?
Question Link
Question Link
What does ASAP mean?
What does ASAP mean?
Question Link
Question Link