Why can I not edit the actual work in Resource Usage view?
Question Link
Answer
We are sorry but we don’t support edits in Resource Usage or on Actual Work field.
How to set the holidays and weekends as nonworking days?
Question Link
Answer
​In order to know how to use the calendars and set holidays and nonworking days, please read the training article: https://www.projectplan365.com/training/lesson-4-define-calendars/.
Under Options, schedule, our project start time has been set to 7am start, 9 hr days, 45 hours per week. When populating Gantt chart there is a unfixable error with the start and finish times.
Question Link
Answer
You need to change the working time for calendars. So, please go to menu Project - Change working time and for the default calendar set the working hours from 7:00 AM to 5:00 PM. Also, please make sure the time of the Start Date for you project is set to 7:00 AM. To check this, go to Project - Project Information and see what is the time you set for Start Date.
Do calendars affect each other?
Question Link
Answer
Calendars override each other's settings in the following ways. When you create a task, the project calendar schedules the task. When you add a resource to a task, the resource calendar controls the scheduling of the task.​
What is a Base Calendar?
Question Link
Answer
Base calendars are the foundations for the other types of calendars. You can choose a base calendar to be the project calendar or to apply a base calendar to tasks as task calendars. Base calendars come in 3 forms : Standard, 24-Hours calendar, Night Shift calendar.
How do Project calendars work?
Question Link
Answer
Project calendars set the standard working and non-working times for the project as a whole. If resource calendars or task calendars are not used, tasks are scheduled during the working time on the project calendar by default.
How set holidays in my Project calendar?
Question Link
Answer

To add a holiday to the Project Calendar click on Project - Change Working Time. In the For calendar list, click the calendar you want to change. For holidays, use the current project calendar. It has the words (Project Calendar) after its name. For vacation days, use the person's resource calendar. It has the same name as that person. On the Exceptions tab, add a name, start date, and finish date for each holiday or vacation day. Project reschedules tasks around the new nonworking time.​

How can I add a base calendar to a resource?
Question Link
Answer
After creating a base calendar for a specialized schedule (other than the Standard project calendar) you can base a resource's working times on this calendar. In the View menu click Resource Sheet. In the Resource Name select the desired resource. In the Base calendar column select the calendar you want to be assigned for the specific resource.
How can I assign a calendar to a task?
Question Link
Answer
To assign a calendar to a task, in the View menu click Gantt Chart. In the Task Name field select the desired task. Open Task Information dialog, on Advanced tab select Base Calendar or insert the Task calendar column in the view and select the desired calendar to the task.
How do I create my own calendar?
Question Link
Answer
To create a customized calendar click on Project - Change Working Time - Create New Calendar. Type the desired name for your new calendar and make sure you checked "Make a copy of standard" option. Change the working days as desired and click OK.
How do I add a specific non-working day?
Question Link
Answer
To create an Exception in your calendar click on Project - Change Working Time - Exceptions. Select a name, start and finish and click Ok.
How do I assign a calendar to a task?
Question Link
Answer
To assign a calendar to a task or to a recurring subtask follow these steps:
1. On the View menu, click Gantt Chart.
2. In the Task Name field, select the task to which you want to assign a calendar.
3. Click Task Information, and then click the Advanced tab.
4. In the Calendar box, click the calendar you want to use for the task.
Can I set a calendar for a summary recurring task?
Question Link
Answer
To assign a calendar to a summary recurring task follow these steps:
1. On the View menu, click Gantt Chart.
2. In the Task Name field, select the summary recurring task to which you want to assign a calendar.
3. Click Task Information.
4. In the Recurring Task Information dialog box, click the calendar you want to assign to the recurring task in the Calendar box.
How can I set the calendar to 7 days per week?
Question Link
Answer
To set the calendar to 7 days per week please click on Project tab - Change Working Time option and from there just click on Works Weeks tab, Details and select Saturday and then enter From-To time for the Saturday and same with Sunday.
How to change the width of an existing column without using the menu tools?
Question Link
Answer
To change the width of an existing column you must hoover over the side edges of the column until the cursor changes into a cross , then by holding the click move the mouse to the left or right, to shrink or to extend.
How to center the name of a column?
Question Link
Answer
To center the name of a column double click on the column , then click on Align Title - Center.
When I hide a column, do I erase all its data?
Question Link
Answer
When you hide a column you do not lose its data. The hide option is designed to cutomise the sheet view and avoid overcrowding.
Can I setup printing to not print all columns?
Question Link
Answer
To not print all columns go to File - Print - Page Setup - View and make sure that ”Print all sheet columns” is cleared out . This option is available only for views with a timescale.
How to change the height of Gantt bars?
Question Link
Answer
To change the height of Gantt bars go into Gantt Chart view then click on Format - Layout and change in the Bar height dialog box the size of the bars then press ok.
How to make the milestones appear as red diamonds in Gantt Chart?
Question Link
Answer
To change the shape or color of a milestone in Gantt Chart go to Format - Bar styles. Click in the row named milestone on the appearance cell corespondent to the row and select the shape and color then press ok.
Which views support style customizations?
Question Link
Answer
The views which can be customized are Gantt Chart, Task Sheet, Resource Sheet and Tracking Gantt.​
How can I customize bar appearance in Gantt Chart or Tracking Gantt views?
Question Link
Answer
The appearance of the task bars can be changed by using the “Bar Styles” or “Bar” options from the “Format” menu. By using the “Bar Styles” option, all the bars belonging to the modified category (milestone tasks, manual tasks, etc) will be changed. By using the “Bar” option, the customizations will only apply to the bar which corresponds to the selected task from grid.
How do I change the appearance of a summary task in Gantt Chart?
Question Link
Answer
To change the appearance for the summary task click on Format - Bar Styles - Summary - Appearance. In the lower bottom of the window modify the appearance as desired then click OK.
How do I change the appearance of the project summary task in Gantt Chart?
Question Link
Answer
To change the appearance for the project summary task click on Format - Bar Styles - Project Summary - Appearance. In the lower bottom of the window modify the appearance as desired then click OK.
How do I change the appearance of a milestone in the Gantt Chart?
Question Link
Answer
To change the appearance for the milestones click on Format>Bar Styles>Milestone>Appearance. In the lower bottom of the window modify the appearance as desired then click OK.