FAQ Project Plan 365
Browse by Category
Why can I not edit the actual work in Resource Usage view?
Why can I not edit the actual work in Resource Usage view?
Question Link
Question Link
How to set the holidays and weekends as nonworking days?
How to set the holidays and weekends as nonworking days?
Question Link
Question Link
Under Options, schedule, our project start time has been set to 7am start, 9 hr days, 45 hours per week. When populating Gantt chart there is a unfixable error with the start and finish times.
Under Options, schedule, our project start time has been set to 7am start, 9 hr days, 45 hours per week. When populating Gantt chart there is a unfixable error with the start and finish times.
Question Link
Question Link
Answer
You need to change the working time for calendars. So, please go to menu Project - Change working time and for the default calendar set the working hours from 7:00 AM to 5:00 PM. Also, please make sure the time of the Start Date for you project is set to 7:00 AM. To check this, go to Project - Project Information and see what is the time you set for Start Date.
Do calendars affect each other?
Do calendars affect each other?
Question Link
Question Link
What is a Base Calendar?
What is a Base Calendar?
Question Link
Question Link
How do Project calendars work?
How do Project calendars work?
Question Link
Question Link
How set holidays in my Project calendar?
How set holidays in my Project calendar?
Question Link
Question Link
Answer
To add a holiday to the Project Calendar click on Project - Change Working Time. In the For calendar list, click the calendar you want to change. For holidays, use the current project calendar. It has the words (Project Calendar) after its name. For vacation days, use the person's resource calendar. It has the same name as that person. On the Exceptions tab, add a name, start date, and finish date for each holiday or vacation day. Project reschedules tasks around the new nonworking time.
How can I add a base calendar to a resource?
How can I add a base calendar to a resource?
Question Link
Question Link
Answer
After creating a base calendar for a specialized schedule (other than the Standard project calendar) you can base a resource's working times on this calendar. In the View menu click Resource Sheet. In the Resource Name select the desired resource. In the Base calendar column select the calendar you want to be assigned for the specific resource.
How can I assign a calendar to a task?
How can I assign a calendar to a task?
Question Link
Question Link
How do I create my own calendar?
How do I create my own calendar?
Question Link
Question Link
How do I add a specific non-working day?
How do I add a specific non-working day?
Question Link
Question Link
How do I assign a calendar to a task?
How do I assign a calendar to a task?
Question Link
Question Link
Answer
To assign a calendar to a task or to a recurring subtask follow these steps:
1. On the View menu, click Gantt Chart.
2. In the Task Name field, select the task to which you want to assign a calendar.
3. Click Task Information, and then click the Advanced tab.
4. In the Calendar box, click the calendar you want to use for the task.
1. On the View menu, click Gantt Chart.
2. In the Task Name field, select the task to which you want to assign a calendar.
3. Click Task Information, and then click the Advanced tab.
4. In the Calendar box, click the calendar you want to use for the task.
Can I set a calendar for a summary recurring task?
Can I set a calendar for a summary recurring task?
Question Link
Question Link
Answer
To assign a calendar to a summary recurring task follow these steps:
1. On the View menu, click Gantt Chart.
2. In the Task Name field, select the summary recurring task to which you want to assign a calendar.
3. Click Task Information.
4. In the Recurring Task Information dialog box, click the calendar you want to assign to the recurring task in the Calendar box.
1. On the View menu, click Gantt Chart.
2. In the Task Name field, select the summary recurring task to which you want to assign a calendar.
3. Click Task Information.
4. In the Recurring Task Information dialog box, click the calendar you want to assign to the recurring task in the Calendar box.
How can I set the calendar to 7 days per week?
How can I set the calendar to 7 days per week?
Question Link
Question Link
How to change the width of an existing column without using the menu tools?
How to change the width of an existing column without using the menu tools?
Question Link
Question Link
How to center the name of a column?
How to center the name of a column?
Question Link
Question Link
When I hide a column, do I erase all its data?
When I hide a column, do I erase all its data?
Question Link
Question Link
Can I setup printing to not print all columns?
Can I setup printing to not print all columns?
Question Link
Question Link
How to change the height of Gantt bars?
How to change the height of Gantt bars?
Question Link
Question Link
How to make the milestones appear as red diamonds in Gantt Chart?
How to make the milestones appear as red diamonds in Gantt Chart?
Question Link
Question Link
Which views support style customizations?
Which views support style customizations?
Question Link
Question Link
How can I customize bar appearance in Gantt Chart or Tracking Gantt views?
How can I customize bar appearance in Gantt Chart or Tracking Gantt views?
Question Link
Question Link
Answer
The appearance of the task bars can be changed by using the “Bar Styles” or “Bar” options from the “Format” menu. By using the “Bar Styles” option, all the bars belonging to the modified category (milestone tasks, manual tasks, etc) will be changed. By using the “Bar” option, the customizations will only apply to the bar which corresponds to the selected task from grid.
How do I change the appearance of a summary task in Gantt Chart?
How do I change the appearance of a summary task in Gantt Chart?
Question Link
Question Link
How do I change the appearance of the project summary task in Gantt Chart?
How do I change the appearance of the project summary task in Gantt Chart?
Question Link
Question Link
How do I change the appearance of a milestone in the Gantt Chart?
How do I change the appearance of a milestone in the Gantt Chart?
Question Link
Question Link