FAQCategory: New ProjectHow to change the work format? I want work to be displayed only in months.

How to change the work format? I want work to be displayed only in months.

1 Answers

To change the work units, go to the File menu – Options (or FileInfoProject Options) and select Schedule tab. From “Work is entered in” select the desired option and then click “OK“.

To change the abbreviations for work units, go to the File menu – Options and select Advanced tab (or FileInfoProject Options – Advanced). From “View Options for time units” select the desired option and then click “OK“.

Contact