How to change the work format? I want work to be displayed only in months.
1 Answers
To change the work units, go to the File menu – Options (or File – Info – Project Options) and select Schedule tab. From “Work is entered in” select the desired option and then click “OK“.
To change the abbreviations for work units, go to the File menu – Options and select Advanced tab (or File – Info – Project Options – Advanced). From “View Options for time units” select the desired option and then click “OK“.