How to show the project summary task?
1 Answers
To see the Summary task for your project, click on File – Options – Advanced (or File – Info – Project Options -Advanced). Make sure the “Show project summary task” is selected and then click OK or by checking the “Project Summary Task” checkbox from the “Format” menu.