How to level manually the resources?
How to level manually the resources?
Question Link
Question Link
Can Project Plan 365 solve automatically the resource overallocation?
Can Project Plan 365 solve automatically the resource overallocation?
Question Link
Question Link
Answer
Project Plan 365 app will not move your task automatically if you have an overallocated resource on two parallel tasks.
The application tells you that you have an overallocated resource by making the entire resource font with red in Resource Sheet view.
In order to solve the overallocation, you need to link the tasks and specify a predecessor.
The application tells you that you have an overallocated resource by making the entire resource font with red in Resource Sheet view.
In order to solve the overallocation, you need to link the tasks and specify a predecessor.
How do I know due tasks not completed?
How do I know due tasks not completed?
Question Link
Question Link
I would like to know how to compare 2 projects?
Can I create a link between tasks in different subprojects?
Can I create a link between tasks in different subprojects?
Question Link
Question Link
Can I insert multiple resources on iPad?
Can I insert multiple resources on iPad?
Question Link
Question Link
Why should I use a password protected file?
Why should I use a password protected file?
Question Link
Question Link
What does the “Compare” functionality do?
What does the “Compare” functionality do?
Question Link
Question Link
Answer
The "Compare" functionality allows reviewing differences between the current version and an earlier or later version of the same project.You can also use this tool to review a current version of a project and one or more projected versions of the same project reflecting different possible scenarios. This may prove useful when evaluating different possible outcomes and potential shortcomings to arise in the future based on the current status.
Custom views created with Project Plan 365 compatible with MS Project?
Custom views created with Project Plan 365 compatible with MS Project?
Question Link
Question Link
How to edit a custom view?
How to edit a custom view?
Question Link
Question Link
How do I create a custom view?
How do I create a custom view?
Question Link
Question Link
How many custom views can I create with Project Plan 365?
How many custom views can I create with Project Plan 365?
Question Link
Question Link
Why and when to use a custom view?
Why and when to use a custom view?
Question Link
Question Link
Answer
A custom view may come in handy when you do not want to modify the standard Gantt Chart by adding customization, alter the table, etc. Think when multiple people work on the same project and they all have different needs and preferences - you just go on and create a custom Gantt Chart that fits your needs and speedup your project analysis process while maintaining the other views clean.
What is a custom view?
What is a custom view?
Question Link
Question Link
What does the Task Burndown chart show in the Burndown report?
What does the Task Burndown chart show in the Burndown report?
Question Link
Question Link
What does the Work Burndown chart show in the Burndown report?
What does the Work Burndown chart show in the Burndown report?
Question Link
Question Link
What charts are available in the Burndown report?
What charts are available in the Burndown report?
Question Link
Question Link
What does the “Burndown” report?
What does the “Burndown” report?
Question Link
Question Link
What is a password protected file?
What is a password protected file?
Question Link
Question Link
What is a resource calendar?
What is a resource calendar?
Question Link
Question Link
What does the “Resource Information” functionality do?
What does the “Resource Information” functionality do?
Question Link
Question Link
My project plan does not take limited ressource into account, means 2 tasks remain in parallel with only 1 ressource allocated 100%. How can I plan my project automatically with limited ressources?
My project plan does not take limited ressource into account, means 2 tasks remain in parallel with only 1 ressource allocated 100%. How can I plan my project automatically with limited ressources?
Question Link
Question Link
Answer
Project Plan 365 app will not move your task automatically if you have the same resource on two parallel tasks.
The application tells you that you have an overallocated resource by making the entire resource font with red in Resource Sheet view.
If you want tasks to be in sequence, you need to link the tasks and specify a predecessor.
Where can I set a Group for my resource?
Where can I set a Group for my resource?
Question Link
Question Link
Where can I find more information about a resource?
Where can I find more information about a resource?
Question Link
Question Link
How do I assign a resource to a summary task?
How do I assign a resource to a summary task?
Question Link
Question Link