FAQ Project Plan 365
Browse by Category
Can I change the table for Resource Usage view?
Can I change the table for Resource Usage view?
Question Link
Question Link
Answer
The Resource Usage view displays categories of information about the resources, arranged in tables. The default table for the Resource Usage view is the Usage table, but you can select any of the resource tables to display information about the project's resources. To do this, go to Project-Table and select the table you want to view.
How to use the Resource Usage view?
How to use the Resource Usage view?
Question Link
Question Link
How to show/hide the “View Bar”?
How to show/hide the “View Bar”?
Question Link
Question Link
What does the “View Bar” functionality do?
What does the “View Bar” functionality do?
Question Link
Question Link
How many types of views are?
How many types of views are?
Question Link
Question Link
What is a View?
What is a View?
Question Link
Question Link
What is a “View Bar”?
What is a “View Bar”?
Question Link
Question Link
How to change the working days for my project?
How to change the working days for my project?
Question Link
Question Link
Answer
In order to change the working days for your project, access Options from the File menu. In the Options dialog, go to the Schedule tab and check the desired working days from the Default working days group. Another way to change the working days is to select a non-working day from the date-picker pop-up in the Start/Finish column and then, in the Alert message select the Adjust the default working days option from which you have to check the desired working days based on your needs.
What does the “Change Working Days” functionality do?
What does the “Change Working Days” functionality do?
Question Link
Question Link
In what views is allowed to insert tasks?
In what views is allowed to insert tasks?
Question Link
Question Link
What happens when I assign a resource to a task?
What happens when I assign a resource to a task?
Question Link
Question Link
How do I create Earned Value report?
How do I create Earned Value report?
Question Link
Question Link
What does the “Earned Value” report?
What does the “Earned Value” report?
Question Link
Question Link
How do I split a task?
How do I split a task?
Question Link
Question Link
How can I move a column in front of another?
How can I move a column in front of another?
Question Link
Question Link
When I hide a column, how can I unhide it?
When I hide a column, how can I unhide it?
Question Link
Question Link
How do I add resources to my project?
How do I add resources to my project?
Question Link
Question Link
Answer
There are multiple ways you can insert resources. Click the View tab and then click on Resource Sheet view. In the Resource Name field, type a work, cost or material resource name. Another possibility of inserting a resource is to use Insert option under Resource tab or press the Insert key on your keyboard. Alternatively, you can right click on the id of a resource and from the contextual menu click on New Resource option from the contextual menu.
How to change the duration of a split task?
How to change the duration of a split task?
Question Link
Question Link
How can bar styles be changed for split tasks?
How can bar styles be changed for split tasks?
Question Link
Question Link
How to remove split task section?
How to remove split task section?
Question Link
Question Link
How do I change the Progress Lines?
How do I change the Progress Lines?
Question Link
Question Link
What does the “Progress Lines” functionality do?
What does the “Progress Lines” functionality do?
Question Link
Question Link
What does the “Gridlines” functionality do?
What does the “Gridlines” functionality do?
Question Link
Question Link
When a row is moved, does the task retain its level
When a row is moved, does the task retain its level
Question Link
Question Link
Answer
Moving a task can change its outline level. A task retains its level in the outline only when you move the task to follow a task at the same level.Comparatively, if you move a lower-level task to a section of tasks at a higher level — for example, move a third-level task to a section of second-level tasks — the moved task takes on the level of the task preceding it. And the converse is true when you move a higher-level task to follow a lower-level task.
What does the “Move column” functionality do?
What does the “Move column” functionality do?
Question Link
Question Link