How to level the entire project?
How to level the entire project?
Question Link
Question Link
Answer
To level the entire project, go to “Team” menu and click the “Level All” button. In the “Resource Leveling” dialog, the “Entire Project” option and click the “OK” button. A summary of how Project Plan 365 fixed the overallocation will be displayed. Click the “OK” button for the changes to be applied.
How to level the tasks of certain resources?
How to level the tasks of certain resources?
Question Link
Question Link
Answer
To level tasks for certain resources, go to “Team” menu and click the “Level Resource” button. In the “Level Resources” dialog, select the resources for which you want to level tasks and click the “OK” button. A summary of how Project Plan 365 fixed the overallocation will be displayed. Click the “OK” button for the changes to be applied.
How to insert the Leveling Delay column?
How to insert the Leveling Delay column?
Question Link
Question Link
When should I use the Leveling Delay field?
When should I use the Leveling Delay field?
Question Link
Question Link
When to use resource leveling?
When to use resource leveling?
Question Link
Question Link
What is resource leveling?
What is resource leveling?
Question Link
Question Link
How to Install Project Viewer 365 for Mac without Erix chatbot?
How to Install Project Viewer 365 for Mac without Erix chatbot?
Question Link
Question Link
How to Install Project Viewer 365 for Mac without any cloud integration?
How to Install Project Viewer 365 for Mac without any cloud integration?
Question Link
Question Link
How do I silently install Project Viewer for Mac?
How do I silently install Project Viewer for Mac?
Question Link
Question Link
What are the available Erix menu options?
What are the available Erix menu options?
Question Link
Question Link
What questions can Erix answer?
What questions can Erix answer?
Question Link
Question Link
Can you send invoice after purchase?
Can you send invoice after purchase?
Question Link
Question Link
Answer
We automatically send to you the invoice attached to the confirmation order email. We send the confirmation order email on the email address you used when you placed the order. You can also download the invoice from Project Plan 365 Portal by going to “Billing” tab – “Your Orders” section and click the “Invoice” action associated with the order you are interested in. Note that only Admins can access the “Billing” tab.
Where can I find all my previous orders?
Where can I find all my previous orders?
Question Link
Question Link
Can I customize cost formula?
How to move the row for multiple tasks?
How do I change the PDF export view?
How to see the percentage of work for each month?
Answer
In order to see the %Work Complete for a specific month, first go to Format menu - Insert, select the %Work Complete column an click OK. Then go to Project menu - Autofilter. Click on the autofilter arrow next to the column heading of the Start column and check only the month you want. The autofilter arrow and the column name will turn in blue.
Can I link other project?
Can I link other project?
Question Link
Question Link
How I can manage a dependency?
How I can manage a dependency?
Question Link
Question Link
Answer
You can manage the Task Dependency between two tasks in 2 ways:
1. From the Task Information Dialog, select a task, from the Task Menu click on Task Information, go to Predecessors tab, add a predecessor, select the Dependency Type and the Lag time if needed.2. In Gantt Chart double-click on the linking arrow between two tasks and from the Task Dependency dialog, select a Dependency Type and Lag time if needed.
1. From the Task Information Dialog, select a task, from the Task Menu click on Task Information, go to Predecessors tab, add a predecessor, select the Dependency Type and the Lag time if needed.2. In Gantt Chart double-click on the linking arrow between two tasks and from the Task Dependency dialog, select a Dependency Type and Lag time if needed.
What is the Critical Path Method?
What is the Critical Path Method?
Question Link
Question Link
Answer
The Critical Path methodology identifies the paths of tasks most likely to impact the project completion date. This technique is used to help project managers to determine the shortest possible project duration and the level of flexibility that exists in the project. The critical path method calculates the early dates (Early Start and Early Finish), late dates (Late Start and Late Finish) and total slack.
How can I change the size of the text in the header/footer on Mac?
How can I change the size of the text in the header/footer on Mac?
Question Link
Question Link
Can you show me a Gantt Chart demo?
Can you show me a Gantt Chart demo?
Question Link
Question Link
Answer
You can read more about the Gantt Chart View in our Gantt Chart Online Article or in our All About Gantt Chart page, which also includes a video.
Is there a training course I can do offline?
Is there a training course I can do offline?
Question Link
Question Link
Answer
We are sorry but at the moment we only offer Online Training Courses and these can be found in our Online Training.
How do I see dependencies?
How do I see dependencies?
Question Link
Question Link
How can I cancel my Business subscription from Microsoft Store?
How can I cancel my Business subscription from Microsoft Store?
Question Link
Question Link
Answer
To cancel the Business Subscription, please go to "Help" menu - "Subscriptions" tab and click the "Cancel Subscriptions" button. Then, follow the instructions from Microsoft Store. We have no access to your account and cannot reach them on your behalf.