FAQs How do I...?

Browse by Category

FAQ › Category: How do I...?
Is it possible to set a task not to start before a certain date?
Question Link
Answer
To set a task no not start before a specified date select the task and click on Task - Task Information - Advanced. Set the Constraint type as Start No Earlier Than and the date under the Constraint date box.
What does FNET mean?
Question Link
Answer
FNET comes from Finish No Earlier Than and is a semi-flexible constraint type. FNET schedules the task to finish on or after a specified date. Use this constraint to ensure that a task does not finish before a certain date.
How do I set a task to not finish before a certain date?
Question Link
Answer
To set a task to not finish before a specified date select the task and click on Task -Task Information - Advanced. Set the Constraint type as Finish No Earlier Than and the date under the Constraint date box.
Is it possible to set a task to not start after a certain date?
Question Link
Answer
To set a task to not start after a specified date select the task and click on Task - Task Information - Advanced. Set the Constraint type as Start No Later Than and the date under the Constraint date box.
What does FNLT mean?
Question Link
Answer
FNLT comes from Finish No Later Than and is a semi-flexible constraint type. FNLT schedules the task to finish on or before a specified date. Use this constraint to ensure that a task does not finish after a certain date.
How do I set a task to not finish after a certain date?
Question Link
Answer
To set a task to not finish after a specified date select the task and click on Task - Task Information - Advanced. Set the Constraint type as Finish No Later Than and the date under the Constraint date box.
What does MFO mean?
Question Link
Answer
MFO comes from Must Finish On and is an inflexible constraint type. MFO schedules the task to finish on a specified date. Sets the early, scheduled and late finish dates to the date that you type and anchors the task in the schedule.
What does MSO stand for?
Question Link
Answer
MSO comes from Must Start On and is an inflexible constraint. MSO schedules the task to start on a specified date. Sets the early, scheduled, and late start dates to the date that you type and anchors the task in the schedule.
What is the most efficient constraint type?
Question Link
Answer
All constraint types have their own role but only the inflexible constraint override any task dependencies and restrict a task to a date you choose.
What role has the slack calculation?
Question Link
Answer
The amount of slack in you schedule indicates how long tasks can be delayed before other tasks or the project finish date are affected. If slack exists in your schedule, you can move tasks when certain phases of the schedule have no slack and other phases have too much.
What amount of slack does a critical task have?
Question Link
Answer
By default a critical task has 0 slack. If the critical task is delayed, the project finish date is also delayed.
What is Total slack?
Question Link
Answer
The total slack of an activity is the time the activity can be delayed without any impact on the finish date of the project.
What is free slack?
Question Link
Answer
Free slack is the amount of time an activity can be delayed without impacting another activity.
How can I make sure that my project finishes on time?
Question Link
Answer
If you want your project to finish on time you can try optimizing tasks that have slack and are not on the critical path.
What is a critical path?
Question Link
Answer
A critical path is a series of tasks that dictates the calculated finish date of the project.
How is % complete calculated?
Question Link
Answer
The % complete has the following formula % complete=(Actual Duration/Duration)*100.
How does the app calculate the start date for a task?
Question Link
Answer
The Start date for a task can be calculated or entered. If you do not type a start date, application calculates a start date based on such things as relationships, calendars, and the scheduling method. If you type a start date, it will be set automatically a Start No Earlier Than constraint which uses the date you type as the constraint date.
How does the app calculate the finish date for a task?
Question Link
Answer
The Finish date for a task can be calculated or entered. The Finish field shows the date when a task is scheduled to be completed. Date the task is scheduled to finish. If you do not type a finish date, application calculates it based on such things as relationships, calendars, and the scheduling method. If resources are assigned, Project also considers the resource calendar and assignment units. If you type a finish date, will be set automatically a Finish No Earlier Than constraint and uses the date you type as the constraint date.
How does the app calculate the duration for a task?
Question Link
Answer
Duration for tasks can be calculated or entered. The duration field is the total span of active working time for a task. Application calculates the duration of a task by counting the amount of active working time between the scheduled start and end of the task.
What is Project Management?
Question Link
Answer
Project Management is a series of activities along the entire lifecycle of a project, meant to ensure that the objectives of the project are accomplished.
What does a Project Manager?
Question Link
Answer
A project manager needs to have knowledge of application, techniques to initiate and plan a project, control its execution, manage resources and close the project.
What is Project Planning?
Question Link
Answer
Project Planning can be defined as a set of activities that aim at developing an action plan which, if followed, ensures that the goals of the project are fulfilled.
What is a Project Planning Tool?
Question Link
Answer
Project Planning Tool is a software used for scheduling, resource allocation and change management. Its main purpose is to facilitate the planning and tracking of project components to be sure it is delivered on time within budget.
What is WBS?
Question Link
Answer
WBS is a decomposition of the entire work of the project on several levels, resulting in a tree structure: the work of the project (first level = root of the tree) is divided in several activities (second level), which, successively may be divided into shorter-term tasks, etc. Successive subdivisions, corresponding to new levels in the tree, may be necessary until the components obtained are manageable in terms of estimates (on duration, costs), work and responsibility.
What are tasks?
Question Link
Answer
A task is an activity in the project necessary to reach the project specific goals. It should always have a clear start and finish date.
Contact
Chat