FAQs How do I...?

Browse by Category

FAQ › Category: How do I...?

Why am I not able to connect to SharePoint?


Question Link
Answer

To open project plans from SharePoint, please follow the steps below:

  1. First, enter the URL address of the SharePoint site in File - Open – SharePoint – SharePoint Settings - OK.
  2. Go to File - Open SharePoint – Open from SharePoint - SharePoint Site - click OK or edit the link as desired.
  3. Type the user and password in the log window.
  4. A list of projects available on SharePoint will be displayed, from where you can choose the project you want to access.

There are several ways to open a project from the Open from SharePoint file picker:

  1. Double click on a project;
  2. Select a project and click Open button;
  3. Right-click on a project and select Open in contextual menu;
  4. Select a project and click Enter key.
How are the Actual Duration and Remaining Duration calculated?
Question Link
Answer

If you type a value in the Percent Complete field, Project Plan 365 automatically calculates actual duration and remaining duration. In this case,

  • Actual Duration = Duration * Percent Complete
  • Remaining Duration = Duration – Actual Duration.

If you type a value in the Percent Complete field in a summary task, Project Plan 365 automatically distributes the Percent Complete for subtasks. The distribution tries to add Actual Duration equally for each subtask which is scheduled as working starting from the Project Start Date.

For more information, please check our Percent Complete online help article.

How to uninstall Project Plan 365?
Question Link
Answer

To uninstall the Project Plan 365 application, follow the steps below:

  1. Windows: Open Start - Control Panel - Programs - Programs and Features. Right-click on Project Plan 365 and then click “Uninstall”.
  2. Mac: Select the app icon from the Applications folder, righ-click on it and from the contextual menu select “Move to Trash”;
  3. Android: Go to your device’s Settings menu - Apps or Application Manager, select Project Plan 365 and touch the “Uninstall” button.
  4. iOS: Hold down the app’s icon in Launchpad until the “Project Plan 365” icon starts to jiggle and then click the app’s delete button (x) to uninstall the app.
How do I Import the team members from my plan into organization?
Question Link
Answer

You will be asked if you want to import Team Members in the following situations:

  1. You save a project in Drive 365 for the first time and you have Work Resources that are not Team Members.
  2. You save an existing project in Drive 365 and you have Work Resources that are not already Team Members.
  3. You share a project with people that are not already Team Members.

To import Team Members manually, go to the menu Team – Import Team. A dialog will appear that will contain all Work Resources in the current project that are not Team Members. Once you enter a valid email address for the resources that you want to import, click on the Add Team Members button. Now the imported resources become Team Members.

How do I setup the real-time collaboration?
Question Link
Answer

To set up any .MPP file for Real-Time Collaboration (rTc), follow this procedure:

  1. Sign In or Sign Up to the Business (PMO) Subscription using your email & password in Project Plan 365 app.
  2. Having the Editor role, open the MPP file that you want to collaborate on with others, and save it to Drive 365 cloud service.
  3. Check off the resources you want to include, and then click on the Add Team Members button.
  4. Open the project from Drive 365. By default, the .MPP file will open in Exclusive Mode, and in order to collaborate with other team members, go to menu Share – Real-Time Collaboration.
  5. Also, you can share the link from your plan with other team members, by using the Share functionality from the Share menu.
How does the Project Plan 365 Scheduling Engine work?
Question Link
Answer

The Project Plan 365 Scheduling engine works as described below:

  1. First Step: Create a graph where nodes are tasks and edges are precedence relations between tasks and do a topological sort to get the order in which we should process the tasks so we calculate early start and early finish dates.
  2. Second Step: Create another graph for successors of tasks and calculate the late start and the late finish dates so we can calculate the real start and finish date of tasks and slack and we can obtain the project durationfinish date and critical path with better accuracy.
  3. Third Step: Compute other task fields like costwork and make sure that resource assignments are calculated correctly.
Can I share a project from the Drive 365?
Question Link
Answer

There are three possibilities you can share your project with your team members or people outside the organization:

  1. By using the Share option from the Share - Share menu;
  2. By clicking on the Share Project button from the Share bar that appears after opening a file;
  3. By going to File menu – Open – My Projects - Drive 365  and in the file picker right-click on the project you want to share and choose Share option from the contextual menu.

Just type the E-mail address and a message, if you want, and click on one of the three options available in the Share Projects with the Team Members dialog: Copy Link, Send as PDF, Send as MPP.For more information, check the Share online help article.

How to add resources for tasks in the Gantt Chart view?
Question Link
Answer

To add resources from the Gantt Chart table, in the Resource Name column, write or select the resource you want to add and set the units or the number of items.To assign resources to tasks in Gantt Chart view, you can import the existing team members from your organization or to add other resources.

  1. To assign an existing team member from your organization to a task, in the Gantt Chart view, click on the down arrow in Resource Names field and from the drop-down list, select a team member (marked with an icon).
  2. To add a resource that is not a team member, simply insert his name in Resource Names field.

Another way to assign a team member or a resource to a task, is to select a task and go to menu Team - Assign - Team Member / Resource.

Why I'm not able to delete a file from Drive 365?
Question Link
Answer
Please know that only the users with Admin rights can delete the files from Drive 365. Contact the owner of the team to give you Admin rights.
How can I change the bar color for multiple individual tasks at the same time?
Question Link
Answer
We are sorry but changing the bar color for multiple individual tasks at the same time, isn’t possible in our application at this point.
On what clouds can I save my projects?
Question Link
Answer
Our application supports saving your .MPP files in the following clouds locations: Drive 365, Google Drive, Dropbox, OneDrive, Project Online/Server, SharePoint, Box, Basecamp.
How do I set days to specific working times?
Question Link
Answer

To change the working times in your calendar, please go to the menu Project menu - Change Working Time. In the Work Weeks tab, click on the Details button and for each working day, set the working hours. For the specific working times to be applied to your project, don’t forget to go to menu File – Options – Schedule tab and change the “Default start time” and “Default end time” values, as well as “Hours per day” and “Hours per week” values to match the set working times. 

Why aren’t the “Top” and “Bottom” bar text options available on Mac?


Question Link
Answer

Please make sure you have our latest version of the application installed on your device: Download Project Plan 365

How do I indicate the time actually spent on the tasks for resources?
Question Link
Answer
To see the actual work performed for a task, you can add the Actual Work field. In the Gantt Chart View, select any field and go to FormatInsert Column. From the Field Name dropdown list select Actual Work.
How can I know the "Planned Percentage Complete" of my project?
Question Link
Answer
Unfortunately, we don’t have a way to do this in Project Plan 365 because we don’t support formulas.
I can't find the Resource Form view in my Mac application.
Question Link
Answer
We are sorry but the Resource Form view isn't available in our Mac application at this moment.
Can't find the Task Form view in the Mac application.
Question Link
Answer
We are sorry but the Task Form view isn't available in our Mac application at this moment.
I have the Business feature but the Resource Leveling functionality is missing.
Question Link
Answer
If the Resource Leveling functionality isn't available in the Project Plan 365 application, please make sure you have the latest version of the application installed on your device: Download
How can I customize the S-Curve report?
Question Link
Answer
We are sorry but the S-Curve Report can't be customized at this point.
How often is the Project Plan 365 application updated?
Question Link
Answer
How often is the Project Plan 365 application updated?
How can I show only the critical tasks in the Network Diagram view?
Question Link
Answer
How can I show only the critical tasks in the Network Diagram view?
How can I identify the critical tasks in the Network Diagram view?
Question Link
Answer
How can I identify the critical tasks in the Network Diagram view?
How can I display "Late Start" and "Late Finish" dates in the Network Diagram view?
Question Link
Answer
We are sorry but the Network Diagram is view-only and displaying "Late Start" and 'Late Finish" dates to the task boxes is not possible at this point.
Why isn't the total cost of a summary task updated when using custom fields?
Question Link
Answer
The Custom fields of Cost type do not automatically calculate the total sum of subtasks of a Summary Task.The only field that works with this formula is the Cost field.Custom Cost fields are used to add custom currency data to an individual task information and does not use the same formula as the Cost field that automatically calculates Summary Tasks value.
How can I create a report only with the columns I need?
Question Link
Answer
To create a report only with the desired columns, go to menu Project - Report - Custom - New. From the "All Columns" section, select the desired fields and move them in the "Report Columns" section. Press "Save" for the changes to apply.
Contact
Chat