Is there any way to filter/highlight tasks that do not have successors?
Question Link
Answer

We don’t have a filter to highlight the tasks without successors but you can use the AutoFilter functionality. In order to do that, go to menu Project-Autofilter. Click on the autofilter arrow next to the “Successor” column heading that contains the information you want to display, and then check the Blank value in order to filter the table.

How do I use the Exclusive and Real-Time Collaboration modes?
Question Link
Answer

There are two modes in which you can open a project from Drive 365: exclusive and real-time collaboration. In the exclusive mode, you are the only one who can edit the project if you are the first editor who opened it. If another editor wants to open the same file, he will have the possibility to edit the file in Read-Only Mode but cannot overwrite it. In real-time collaboration mode, multiple team members can make changes to the same project at the same time. Only a team member with an Editor role can enter in exclusive or real-time collaboration mode. As an editor, when opening a project from Drive 365, it will be automatically opened in Exclusive mode if the file is not opened in Exclusive mode by another team member. If the file is already opened in exclusive mode by another team member, you will receive the following message:“Currently the project is opened by … in Editing Mode. Click ‘Read-Only’ to open the file in read-only mode.” Click on the Read-Only button to open the project. You will be able to edit the file but won’t be able to save it over the original file from Drive 365, instead you can save it to a different storage location. Click on the Cancel button if you don’t want to open the project in Read-Only mode. If the file is already opened in Real-Time Collaboration mode, you will automatically enter also in Collaboration mode. 

On what platforms is the “Save Password Protected .MPP files” feature available?
Question Link
Answer

The “Save Password Protected .MPP files” feature in currently available only for Windows, Web, iOS and Mac applications.

Why isn’t the “Clear Formatting” option available in Font Control?


Question Link
Answer

If the “Clear Formatting” option isn’t available in Font Control, please make sure you have the latest version of the application installed on your device: Download.

Where do I find the "Clear Formatting" option?


Question Link
Answer

The “Clear Formatting” option can be found by accessing Task Menu – Font control. Please know that it is currently only available for the Mac and Windows applications.

How do I format the Team Planner view?
Question Link
Answer
We are sorry, but at this point, you cannot format the Team Planner View.
Can I print to A2 format on Windows?
Question Link
Answer

In order to print in A2 format on Windows, please follow these steps:
1. Download and install the free CutePDF Writer software.
2. Open Project Plan 365 app.
3. Go to File - Print - Page Setup
4. Select Options and on Printer field select CutePDF Writer, then press OK.
5. On paper size select ISO A2.

How can I change the timescale from months to weeks?
Question Link
Answer
In order to change the Timescale to weeks instead of months, go to the Format menu and then select the Timescale option. Click on Bottom Tier tab, from "Units" field select "Weeks" and then click OK.
How can I have all the documents saved in one place and after that use them for my projects?
Question Link
Answer
You can save them in one of the clouds available in our application, Google Drive, One Drive, Dropbox, etc. and then you add a hyperlink with the desired document to the tasks in your project. You can read more information about hyperlinks from our Hyperlink online help article.
How can I print the Backlog Board?
Question Link
Answer
We are sorry but printing the Backlog Board is not possible at this point in our application.
How can I change % complete to multiple tasks?
Question Link
Answer
We are sorry, but at this point our application you can't change the % complete for multiple tasks at the same time.
How do I add the Task Name inside the Bar in the Tracking Gantt view?
Question Link
Answer
To add the Task Name inside the bar in Tracking Gantt view, go to the Format tab, click Bar Styles- select the type of Gantt bar – click Text tab – on the Inside field select Name – click OK.
On which views is the “Clear Formatting” option available?
Question Link
Answer
The “Clear Formatting” option is available for the views that support style customization: Gantt Chart, Resource Sheet, Tracking Gantt, Task Sheet, Risk View, Timeline.
How do I remove formatting changes for an entire column?
Question Link
Answer
In order to remove formatting for an entire column, select the column and then from the Task Menu – Font Control, click the “Clear Formatting” button.
How do I remove formatting for a task in Timeline view?
Question Link
Answer
In order to remove formatting applied to a task in Timeline view, select the desired task and then, from Task menu – Font Control, click the “Clear Formatting” option.
How do I remove formatting applied using the Text Styles dialog?
Question Link
Answer
Formatting applied using the Text Styles dialog cannot be removed using the “Clear Formatting” option.
How do I remove formatting for multiple rows?
Question Link
Answer
To remove formatting for multiple rows, select the rows, then go to Task menu – Font Control and click the “Clear Formatting” button.
How do I remove formatting for multiple cells?
Question Link
Answer
To remove formatting for multiple cells, select the cells, then go to Task menu – Font Control and click the “Clear Formatting” button.
How do I remove formatting in Real-Time Collaboration?
Question Link
Answer
How do I remove formatting in Real-Time Collaboration?
How do I remove formatting for a specific row?
Question Link
Answer
In order to remove formatting for a specific row, select the entire row, then go to Task menu and from Font Control, click the “Clear Formatting” button.
How do I remove formatting for a specific cell?
Question Link
Answer
In order to remove formatting for a specific cell, click on the cell, then go to Task menu and from Font Control, click the “Clear Formatting” button.
What does the “Clear Formatting” functionality do?
Question Link
Answer
The “Clear Formatting” option removes any custom formatting from the selection.
How do I print the Resource Usage view?
Question Link
Answer
To print the Resource Usage view, open the application, make sure the selected view is Resource Usage and then go to the File menu - Print and select the Print option.
Can I Schedule Reports for Password Protected MPP Files?
Question Link
Answer
We are sorry but Password Protected MPP Files are not supported by the Scheduled Reports functionality. If you do add password protected MPP file to scheduled reports, the report will not be sent and Preview will be unavailable!
What does the "Custom Field" tab in Resource Information dialog do?
Question Link
Answer
The Custom Field tab in "Resource Information" dialog displays the custom resource fields available your project.