I need to see the cost instead of hours in the Task Usage view.
I need to see the cost instead of hours in the Task Usage view.
Question Link
Question Link
How can I show the Resource Initials next to the bars?
How can I show the Resource Initials next to the bars?
Question Link
Question Link
Answer
In order to add the Resource initials in the Gantt Chart, go to the Format menu – Bar styles, select the Text tab, chose in which side of the Gantt Chart you want to display the Resource name initials and select the “Resource Initials” field. Press “OK” and the Resource Initials will be displayed in the Gantt Chart.
How to save a project file to Google Drive?
How to save a project file to Google Drive?
Question Link
Question Link
How to save a project file to Dropbox?
How to save a project file to Dropbox?
Question Link
Question Link
How do I open a password protected subproject?
How do I open a password protected subproject?
Question Link
Question Link
Answer
To open a password protected subproject, go to “Project” – “Subproject” – “Computer” / “Drive 365” and choose the desired project from local device or “Drive 365” cloud. Click the “Open” button, and then type the password in “Password” dialog. The subproject will be added to your master project.
How do I open a password protected project plan?
How do I open a password protected project plan?
Question Link
Question Link
How can I save my files to SharePoint Site?
How can I save my files to SharePoint Site?
Question Link
Question Link
Answer
In order to save your files to SharePoint, go to the File menu - Save As (also click the Other Locations dropdown if on Mac) - SharePoint, choose SharePoint Site, enter the URL address of the SharePoint site, authenticate with your Microsoft account if not authenticated, type the name of the file and press "Save".
How can I save files to iCloud Drive?
How can I save files to iCloud Drive?
Question Link
Question Link
I used the Silent Install command with license key but the key wasn’t applied to the application.
I used the Silent Install command with license key but the key wasn’t applied to the application.
Question Link
Question Link
How do I permanently renumber task IDs when sorting by start date?
How do I permanently renumber task IDs when sorting by start date?
Question Link
Question Link
Answer
When using the Sort functionality the tasks are rearranged in the current view based on the specified criteria. When sorting the tasks by Start Date the task IDs are automatically rearranged.
We are sorry but at this point it is not possible to sort by date and also rearrange the task IDs in numerical order. They only appear in numerical order only when you are using the “sort by ID” option.
We are sorry but at this point it is not possible to sort by date and also rearrange the task IDs in numerical order. They only appear in numerical order only when you are using the “sort by ID” option.
Can I export to PowerPoint on Mac?
Can I export to PowerPoint on Mac?
Question Link
Question Link
Is there an option to set work contour for my project?
The Critical Path option is grayed out and not accessible.
The Critical Path option is grayed out and not accessible.
Question Link
Question Link
How to remove slack?
How to remove slack?
Question Link
Question Link
What does the yellow diamond icon mean?
What does the yellow diamond icon mean?
Question Link
Question Link
How to assign a task in Team Planner View?
How to assign a task in Team Planner View?
Question Link
Question Link
Is it possible to store our subprojects in SharePoint?
Is it possible to store our subprojects in SharePoint?
Question Link
Question Link
Where can I find the Erix project status list?
Where can I find the Erix project status list?
Question Link
Question Link
Answer
To see the Erix Project Status List, go to Erix Project Status List help article on our website.
How to Install Project Viewer 365 with Erix chatbot and selected clouds?
How to Install Project Viewer 365 with Erix chatbot and selected clouds?
Question Link
Question Link
How to Install Project Viewer 365 with Erix chatbot but no clouds?
How to Install Project Viewer 365 with Erix chatbot but no clouds?
Question Link
Question Link
How to Install Project Viewer 365 without Erix chatbot?
How to Install Project Viewer 365 without Erix chatbot?
Question Link
Question Link
Is there a way to add ‘Cost’ in the right side of the Resource Usage view?
Is there a way to add 'Cost' in the right side of the Resource Usage view?
Question Link
Question Link
How can I change the timescale to quarters?
How can I change the timescale to quarters?
Question Link
Question Link
How to customize the timescale?
How to customize the timescale?
Question Link
Question Link