FAQs How do I...?

Browse by Category

FAQ › Category: How do I...?
How the Duration of a task is calculated?
Question Link
Answer
Duration for tasks can be calculated or entered. Application calculates the duration of a task by counting the amount of active working time between the scheduled start and end of the task. This is generally the time from task start to finish, not counting nonworking time.Tip: Enter the duration for tasks when you create the tasks. The Duration field is one of the major elements for scheduling calculations. It is the span of time shown by the Gantt bars on the Gantt Chart.
What does the Duration field show?
Question Link
Answer
The Duration field is the total span of active working time for a task. This is generally the amount of working time from the start to the finish of a task.
What does the Finish field show?
Question Link
Answer
The Finish field shows the date when a task is scheduled to be completed.
How a Start date for a task is calculated?
Question Link
Answer
A Start date can be calculated or entered. If you do not type a start date, application calculates a start date based on such things as relationships, calendars, and the scheduling method. If you type a start date, will be set automatically a Start No Earlier Than constraint and uses the date you type as the constraint date.
What does the Start field show?
Question Link
Answer
The Start field shows the date when an assigned resource is scheduled to begin working on a task.
When I should use Peak Units field (assignment-timephased field)?
Question Link
Answer
Add the Peak Units field to the timephased portion of the Task Usage or Resource Usage view when you want to display the maximum effort for which the resource is designated to work on an assignment, as distributed over time. This is particularly useful when you have applied a work contour other than the default flat work contour. The Peak Units field shows the points in time in which more effort is being applied to the assignment.
How Peak Units field (assignment-timephased field) is calculated?
Question Link
Answer
The value in the Peak Units field represents the maximum effort a resource is working on an assignment in the given time period.
When I should use Peak Units field (resource-timephased field)?
Question Link
Answer
Add the Peak Units field to the timephased portion of the Resource Usage view when you want to display the maximum effort for which the resource is designated to work on all assigned tasks over the selected time period.
How Peak Units field (resource-timephased field) is calculated?
Question Link
Answer
The value in the Peak Units field is the maximum effort a resource is working on all assigned tasks, as shown over a period of time.
How many categories of Peak Units fields are there?
Question Link
Answer
There are two categories of Peak Units fields (resource-timephased field and assignment-timephased field).
What do the Peak Units fields show?
Question Link
Answer
The Peak Units fields contain the percentage or number of units to which a resource is assigned at any one time for tasks as distributed over time.
If I want to move the project, will the deadlines also move?
Question Link
Answer
When moving the project, you will be able to select to also move or not the deadlines.
How do I set a deadline for a task?
Question Link
Answer
To set a deadline for a task, go to Task Information dialog – Advanced tab and select a date for the Deadline field.
What does the “Deadlines” functionality do?
Question Link
Answer
The Deadlines functionality allows you to set a date by which a certain task/deliverable/milestone must be finished, i.e. a deadline.
How to access Project Plan 365 Portal page?
Question Link
Answer
Please click on the following link to access our Online Portal page: https://www.projectplan365.com/ups/Account/SignIn
How to plan expenses related to the purchase of equipment and materials needed to implement projects?
Question Link
Answer
For expenses related to the purchase of equipment (fixed cost), in Resource Sheet view you can add a resource of type cost. Then, you can assign that resource to a specific task in Task Information dialog under Team tab.
How can I plan and control equipment orders and deliveries (logistics activities) in the project?
Question Link
Answer
For material resources, in Resource Sheet you can add a resource of type material. Insert the material label and the Std. Rate. In Gantt Chart view or in Task information dialog you can specify the units for that specific material.
How can I see the resources grouped by resource type at a specific date in the project?
Question Link
Answer
We are sorry, but at this point our application doesn't allow to see the resources grouped by resource type at a specific date.
How can I add another project to an existing Dashboard Project?
Question Link
Answer
In order to add another project to an existing Dashboard project, go to the Report menu - Dashboard and click on "Open from Computer" button - select the XML file and press Open. Then open again the Dashboard dialog and add another project and click on "View".
How to manage project delays?
Question Link
Answer
To register the delays on a specific task, after you finished your schedule, please set a baseline by going to menu Project – Set Baseline.After this, if you have a delay on a task, change the Start or Finish date. In this way, the Planned Start is the Baseline Start and the Actual Start is the Start date.
Where can I save a MPP file so I can open it from all my devices?
Question Link
Answer
In order to open the mpp file on all your devices, please save the mpp file in Drive 365 cloud. Then, you will be able to see the file on any other device with
a simple Sign in inside the application.
How can I generate a report that states one work week?
Question Link
Answer
You can generate a report called Who Does What When report by going to menu Report – Assignments -Who Does What When Report and click on the Select button.
How can I open a MPP from my iPad?
Question Link
Answer
To open a MPP file on iPad, just open the Project Plan 365 app and go to menu File – Open – Device – navigate to the location where your file is saved.
How can I edit a custom field in Task Information dialog?
Question Link
Answer
Our application doesn’t support to edit the custom fields in Task information dialog.To edit the custom field, please insert that specific field in Gantt Chart view by going to menu Format – Insert Column.
How can I enable auto updates so I can get the latest version of the application?
Question Link
Answer
We don’t have an automatic update feature, if you want to install our latest version, you need to manually uninstall the old version and install the latest
version from our website.
Contact
Chat