FAQs How do I...?

Browse by Category

FAQ › Category: How do I...?
What is SV Percent (%) field?
Question Link
Answer
The SV% (schedule variance percent) field shows the ratio of schedule variance (SV) to budgeted cost of work scheduled (BCWS), expressed as a percentage.
What is SV field?
Question Link
Answer
The SV (earned value schedule variance) field shows the difference in cost between the current progress and the baseline plan of a task, all assigned tasks of a resource, or for an assignment up to the status date or today's date.
What is Summary Progress field?
Question Link
Answer
The Summary Progress field shows the progress on a summary task, based on the progress of its subtasks and where these subtasks have been scheduled.
What is Summary field?
Question Link
Answer
The Summary field indicates whether a task is a summary task.
What is Successors field?
Question Link
Answer
The Successors field lists the task ID numbers for the successor tasks to a task.
What is Subproject Read Only field?
Question Link
Answer
The Subproject Read Only field indicates whether the subproject of this task is a read-only project.
What is Subproject File field?
Question Link
Answer
The Subproject File field contains the name of a project inserted into the active project file.
What is Stop field?
Question Link
Answer
The Stop field shows the date that represents the end of the actual portion of a task.
What is Status Manager field?
Question Link
Answer
The Status Manager field contains the name of the enterprise resource who is to receive status updates for the current task from resources working in Microsoft Project Web App.
What is Status Indicator field?
Question Link
Answer
The Status Indicator field displays an icon that represents the current status of a task.
What is Status field?
Question Link
Answer
The Status field indicates the current status of a task: Complete, On Schedule, Late, or Future Task.
What is Start1-10 field?
Question Link
Answer
The Start1 through Start10 fields show any specific task, resource, or assignment start date information that you want to enter and store separately in your project.
What is Start Variance field?
Question Link
Answer
The Start Variance field contains the time that represents the difference between a baseline start date of a task or assignment and its currently scheduled start date.
What is Start Slack field?
Question Link
Answer
The Start Slack field contains the duration between the Early Start and Late Start dates.
What is Start field?
Question Link
Answer
The Start field shows the date when an assigned resource is scheduled to begin working on a task.
What is Standard Rate field?
Question Link
Answer
The Standard Rate field shows the rate of pay for regular, non-overtime work performed by a resource.
What is Sprint field?
Question Link
Answer
The Scheduled Start field indicates the date when work on a task is scheduled to begin as calculated by Microsoft Project, based on dependencies, constraints, calendars, and other scheduling factors.
What is SPI field?
Question Link
Answer
The SPI (schedule performance index) field shows the ratio of the budgeted cost of work performed to the budgeted cost of work scheduled (BCWP/BCWS).
What is Scheduled Start field?
Question Link
Answer
The Scheduled Start field indicates the date when work on a task is scheduled to begin as calculated by Microsoft Project, based on dependencies, constraints, calendars, and other scheduling factors.
What is Scheduled Finish field?
Question Link
Answer
The Scheduled Finish field indicates the date when work on a task is scheduled to be complete as calculated by Microsoft Project based on the start date, duration, dependencies, calendars, and other scheduling factors.
What is Scheduled Duration field?
Question Link
Answer
The Scheduled Duration field shows the total span of active working time for a task as entered or as calculated by Microsoft Project based on start date, finish date, calendars, and other scheduling factors.
What is Rollup field?
Question Link
Answer
For subtasks, the Rollup field indicates whether information about the subtask Gantt bars will be rolled up to the summary task bar
What is Resume field?
Question Link
Answer
The Resume field shows the date that the remaining part of a task is scheduled to resume after you enter any progress, for example, % Complete, % Work Complete, Actual Work, Actual Duration, or Actual Start.
What is Response Pending field?
Question Link
Answer
The Response Pending field indicates whether an acknowledgement has been received from team members assigned to tasks.
What is Resource Type field?
Question Link
Answer
The Resource Type field indicates whether resources assigned to this task/assignment are work or material resources.