How to create an Outline structure?
Question Link
Answer
To create an outline structure, select the desired tasks then use indenting and outdenting functionality to create the summary tasks and subtasks.
How to create a summary task?
Question Link
Answer
To create a summary task, indent a task below another task. By default, the summary tasks are bold and outdented, and the subtasks are indented beneath them.
How to apply a filter?
Question Link
Answer
In order to apply a filter, select the Filter option under the Format menu and click a filter in the filter list. To apply a filter that isn’t in that list, click More filters, select a filter and then click Apply.
How do I use the “Go To” functionality?
Question Link
Answer

To use the Go To window go to menu Project - Go To. Select the desired ID or date and click OK.

How do I unhide a row?
Question Link
Answer
Please check if you have a filter or an auto filter applied to your file. In order to check this, go to menu Project-Filter and select All Tasks.
How can I set the status date?
Question Link
Answer
In order to set the status date, please go to menu Project - Project Information.
How can I set my project working hours only for night shifts?
Question Link
Answer
To change the calendar of your project go to Project - Project Information - Calendar - Night Shift.
How can I see only particular information from my project?
Question Link
Answer
When you want to see a particular type of information you need to use filters. The application provides Predefined filters as well as Custom filters and Auto filters.
How can I highlight tasks that have a certain property?
Question Link
Answer
To highlight tasks with a certain property click on Project - Filter - More Filters. Select a filter in the filter list and then click Highlight.
How can I apply an AutoFilter?
Question Link
Answer

In order to apply an autofilter, go to menu Project-Autofilter. Click on the autofilter arrow next to the column heading that contains the information you want to display, and then check the values in order to filter the table. The autofilter arrow and the column name will turn in blue.

How can a group be applied?
Question Link
Answer
Tasks or resources can be grouped by selecting the “Group” option from the “Project” menu. Then, after selecting the desired group from the list or from the “More groups” dialog, the tasks or resources will be grouped and the changes will be applied to the current view.
How are the summary task values calculated?
Question Link
Answer

Not all summary task values show the combined total of your subtask values. Although some summary task values (such as cost and work) represent the total subtask values, others (such as duration and baseline) do not. For example, application calculates the duration of a summary task as the total work time between the earliest start date and the latest finish date of its subtasks.

The summary task information summarizes the period between the earliest start date and the latest finish date of all the included subtasks. It does not show the sum of all the subtask durations. Because application calculates the summary task values, they cannot be edited. If you need to change a summary task's values, such as duration, update the individual subtasks. Summary task values are then recalculated.

How can I start record the progress of the work made on the project?
Question Link
Answer

To record the progress of the work made on tasks you need to modify the Percent Complete field for tasks. You can change the %complete from Gantt Chart by adding the %complete field or you can insert the %complete in Task Information dialog.

How do I remove an autofilter on a specific column?


Question Link
Answer
In order to remove the filtering on a specific row, click Clear All Filters in the AutoFilter list for that field.
In what views can I apply the task filters?
Question Link
Answer
Task Filters are available for Gantt Chart, Network Diagram, Task Usage and Tracking Gantt under the Project toolbar.
How do I export the project so without it looking so horizontal?
Question Link
Answer
You can set the Timescale in Gantt Chart view to a bigger Unit like months, quarters or years.
What role do checboxes have when I apply an autofilter?
Question Link
Answer
The checkboxes allow you to select what values to be displayed by simply checking/unchecking the values.
How do I know that an autofilter is applied?
Question Link
Answer
When an autofilter is applied, the column header is displayed in blue text color.
How do I apply the "Using Resource" filter?
Question Link
Answer
In order to apply the "Using Resource" filter, go to menu Project - Filter and select More Reports then select Using Resource and click on Apply button.
What does the "Using Resource" filter do?
Question Link
Answer
The "Using Resource" filter allows seeing all tasks that use the specified resource.
What does the "Using Resource in Date Range…" filter do?
Question Link
Answer
The "Using Resource in Date Range…" filter allows seeing the tasks allocated to a specified resource within a specified date range.
What does the "Tasks/Assignments with Overtime" filter do?
Question Link
Answer
The "Tasks/Assignments with Overtime" filter allows seeing all tasks or assignments that are specified as overtime work.
What does the "Summary Task with Assigned Resources" filter do?
Question Link
Answer
The "Summary Task with Assigned Resources" filter allows seeing the tasks with subtasks who don’t have resources assigned.
What does the "Overallocated Tasks" filter do?
Question Link
Answer
The "Overallocated Tasks" filter allows seeing the tasks that are overallocated because a resource works more than 100% on it.
What does the "No Resource Assigned" filter do?
Question Link
Answer
The "No Resource Assigned" filter allows seeing the tasks that have no resources assigned.