What is Baseline0-10 Estimated Finish field?
What is Baseline0-10 Estimated Finish field?
Question Link
Question Link
Answer
When you set a baseline, Microsoft Project copies the Scheduled Finish dates for a task or assignment and stores them in the Baseline Estimated Finish fields (Baseline Estimated Finish to Baseline1 Estimated Finish through Baseline10 Estimated Finish). This is true whether the tasks are manually or automatically scheduled.
What is Baseline0-10 Estimated Duration field?
What is Baseline0-10 Estimated Duration field?
Question Link
Question Link
Answer
The Baseline0-10 Estimated Duration fields show the approximated span of time planned to complete a task. When you set a baseline, Microsoft Project copies the Scheduled Duration values for tasks and stores them in the Baseline Estimated Duration fields (Baseline Estimated Duration to Baseline1 Estimated Duration through Baseline10 Estimated Duration). This is true whether the tasks are manually or automatically scheduled.
What is Baseline0-10 Cumulative Work field field?
What is Baseline0-10 Cumulative Work field field?
Question Link
Question Link
What is Baseline Work field?
What is Baseline Work field?
Question Link
Question Link
What is Baseline Start field?
What is Baseline Start field?
Question Link
Question Link
What is Baseline Finish field?
What is Baseline Finish field?
Question Link
Question Link
What is Baseline Duration field?
What is Baseline Duration field?
Question Link
Question Link
What is Baseline Deliverable Start field?
What is Baseline Deliverable Start field?
Question Link
Question Link
What is Baseline Deliverable Finish field?
What is Baseline Deliverable Finish field?
Question Link
Question Link
What is Baseline Cost field?
What is Baseline Cost field?
Question Link
Question Link
What is Baseline Budget Work field?
What is Baseline Budget Work field?
Question Link
Question Link
What is Baseline Budget Cost field?
What is Baseline Budget Cost field?
Question Link
Question Link
What is Base Calendar field?
What is Base Calendar field?
Question Link
Question Link
What is Available To field?
What is Available To field?
Question Link
Question Link
What is Available From field?
What is Available From field?
Question Link
Question Link
What is Assumptions field?
What is Assumptions field?
Question Link
Question Link
What is Assignment Units field?
What is Assignment Units field?
Question Link
Question Link
What is Assignment Owner field?
What is Assignment Owner field?
Question Link
Question Link
What is Assignment field?
What is Assignment field?
Question Link
Question Link
What is Assignment Delay field?
What is Assignment Delay field?
Question Link
Question Link
What is Areas Impacted field?
What is Areas Impacted field?
Question Link
Question Link
What is ACWP field?
What is ACWP field?
Question Link
Question Link
What is Actual Work field?
What is Actual Work field?
Question Link
Question Link
What is Actual Start field?
What is Actual Start field?
Question Link
Question Link
What is Actual Overtime Work field?
What is Actual Overtime Work field?
Question Link
Question Link