How do I create Overbudget Tasks report?
Question Link
Answer

In order to create the Overbudget Tasks report for your plan, go to menu Report - Costs - Overbudget Tasks.

What does the “Overbudget Tasks” report?
Question Link
Answer

The "Overbudget Tasks" report displays the tasks whose costs are greater than their baseline costs.

How do I create Budget report?
Question Link
Answer

In order to create the Budget report for your plan, go to menu Report – Costs – Budget Report.

What does the “Budget” report?
Question Link
Answer

The "Budget" report displays the costs per tasks on a weekly basis.

How do I create Cash Flow report?
Question Link
Answer

In order to create the Cash Flow report for your plan, go to menu Report - Costs - Cash Flow.

What does the “Cash Flow” report?
Question Link
Answer

The "Cash Flow" report displays the costs per tasks on a weekly basis.

How do I create Slipping Tasks report?
Question Link
Answer

In order to create Slipping Tasks report for your plan, go to menu Report – Current Activities - Slipping Tasks.

What does the “Slipping Tasks” report?
Question Link
Answer

The "Slipping Tasks" report displays the list of tasks that were rescheduled to finish after their baseline plan.

How do I create Should Have Started Tasks report?
Question Link
Answer

In order to create the Should Have Started Tasks report for your plan, go to menu Report – Current Activities - Should Have Started Tasks.

What does the “Should Have Started Tasks” report?
Question Link
Answer

The "Should Have Started Tasks" report displays the tasks that should have started by a specified date.

How do I create Completed Tasks report?
Question Link
Answer

In order to create the Completed Tasks report for your plan, go to menu Report – Current Activities - Completed Tasks.

What does the “Completed Tasks” report?
Question Link
Answer

The "Completed Tasks" report displays a list with task information for tasks that are 100% complete (have both actual start and finish dates saved).

How do I create Tasks in Progress report?
Question Link
Answer

In order to create the Tasks in Progress report for your plan, go to menu Report – Current Activities - Tasks in Progress.

What does the “Tasks in Progress” report?
Question Link
Answer

The "Tasks in Progress" report displays a list with task information for tasks that have the % complete value between 1 and 99 (have an actual start date but no actual end date saved).

How do I create Tasks Starting Soon report?
Question Link
Answer

In order to create the Tasks Starting Soon report for your plan, go to menu Report - Current Activities - Tasks Starting Soon.

What does the “Tasks Starting Soon” report?
Question Link
Answer

The "Tasks Starting Soon" report displays the tasks starting within a specified timescale.

How do I create an Unstarted Tasks report?
Question Link
Answer

In order to create the Unstarted Tasks report for your plan, go to menu Report – Current Activities - Unstarted Tasks.

What does the “Unstarted Tasks” report?
Question Link
Answer

The "Unstarted Tasks" report displays a list with information for tasks that have 0% complete (have no actual start date saved).

How do I create a Working Days report?
Question Link
Answer

In order to create the Working Days report for your plan, go to menu Report – Overview- Working Days.

What does the “Working Days” report?
Question Link
Answer

The "Working Days" report displays the working days for the base calendar with their exceptions.

How do I create a Milestone report?
Question Link
Answer

In order to create a Milestones report, go to menu Report - Overview - Milestones.

What does the “Milestones” report?
Question Link
Answer

The “Milestones” report displays the list of milestones from your project sorted by start date.

How do I create a Critical Tasks report?
Question Link
Answer

In order to create the Critical Tasks report for your plan, go to menu Report - Overview - Critical Tasks.

What does the “Critical Tasks” report?
Question Link
Answer

The "Critical Tasks" report displays the list of critical tasks in project with their start and finish dates, successors, resources and so on.

How do I create a Top-Level Tasks report?
Question Link
Answer

In order to create the Top-Level Tasks report for your plan, go to menu Report - Overview - Top Level Tasks.