FAQs Scheduling
Browse by Category
FAQ › Category: How do I...? › Scheduling
How can I see the Early Start for tasks?
How can I see the Early Start for tasks?
Question Link
Question Link
What does the “Early Start and Early Finish fields calculation” do?
What does the “Early Start and Early Finish fields calculation” do?
Question Link
Question Link
Answer
When you first create a task, its early start and early finish dates are the same as the scheduled start and finish dates. As you link the task to predecessor and successor tasks and apply any date constraints, the early start and early finish dates are calculated as the earliest possible dates this task could start and finish if all predecessors and successors also start and finish on their respective early start and early finish dates. If there is a leveling delay on the task, this delay is also figured into the early start and finish dates. These calculations are based on a fixed duration.
How can I see the Cost Assignment on tasks?
How can I see the Cost Assignment on tasks?
Question Link
Question Link
How are Rate-based and Per-use costs applied to Work Resources and Material Resources?
How are Rate-based and Per-use costs applied to Work Resources and Material Resources?
Question Link
Question Link
Answer
The Rate-based cost as well as the Per-use cost operate in different ways, depending upon whether the resource is a work resource (a person, rental equipment etc.) or a material resource.The Standard Rate cost is Applied per hour for Work Resources and per unit assignment for Material Cost.The Per Use cost, for Material Resources applied once per assignment and for Work Resources depends on the assignment units used.A resource can have both a rate-based cost and a per-use cost set up
What is Rate-based cost?
What is Rate-based cost?
Question Link
Question Link
What do “Cost” represent in Project Plan 365?
What do “Cost” represent in Project Plan 365?
Question Link
Question Link
What does the “Calculation Duration, Start and Finish” functionality do?
What does the “Calculation Duration, Start and Finish” functionality do?
Question Link
Question Link
Answer
The “Calculation Duration, Start and Finish”, as the names describes, calculates the start and finish dates of tasks considering factors like constraints, linked tasks or other. For optimal scheduling flexibility, it's recommended that you allow application to calculate the start and finish dates for tasks based on the durations and task dependencies you enter. If you have unavoidable constraints, such as an event date, you can set a specific start or finish date for a task.
What information does the Variance table provide?
What information does the Variance table provide?
Question Link
Question Link
How can I compare the baseline and the scheduled information?
How can I compare the baseline and the scheduled information?
Question Link
Question Link
How can I know that a task is inactive?
How can I know that a task is inactive?
Question Link
Question Link
How can I inactivate a task?
How can I inactivate a task?
Question Link
Question Link
How can I move a task? It keeps the start date and duration as priority, rather then logic links I am giving with predecessors.
How can I move a task? It keeps the start date and duration as priority, rather then logic links I am giving with predecessors.
Question Link
Question Link
Answer
If a task has any actuals applied, such as an actual start date or a percentage of work completed, the task can't be rescheduled any earlier than the date when the task actually began. If no progress is entered and the task has an inflexible constraint, the constraint can take precedence over task dependencies. Please remove % complete values then try again to change predecessors value.
What role do Constraints have?
What role do Constraints have?
Question Link
Question Link
How does the flexible constraints affect tasks?
How does the flexible constraints affect tasks?
Question Link
Question Link
When should I use semi-flexible constraints?
When should I use semi-flexible constraints?
Question Link
Question Link
When should I use inflexible constraints ?
When should I use inflexible constraints ?
Question Link
Question Link
How do I make my project as flexible as possible ?
How do I make my project as flexible as possible ?
Question Link
Question Link
Where do I see the constraint type of a task?
Where do I see the constraint type of a task?
Question Link
Question Link
What does ALAP mean?
What does ALAP mean?
Question Link
Question Link
What does ASAP mean?
What does ASAP mean?
Question Link
Question Link
What does SNET mean?
What does SNET mean?
Question Link
Question Link
Is it possible to set a task not to start before a certain date?
Is it possible to set a task not to start before a certain date?
Question Link
Question Link
What does FNET mean?
What does FNET mean?
Question Link
Question Link
How do I set a task to not finish before a certain date?
How do I set a task to not finish before a certain date?
Question Link
Question Link
Is it possible to set a task to not start after a certain date?
Is it possible to set a task to not start after a certain date?
Question Link
Question Link