How are the Actual Duration and Remaining Duration calculated?
Question Link
Answer

If you type a value in the Percent Complete field, Project Plan 365 automatically calculates actual duration and remaining duration. In this case,

  • Actual Duration = Duration * Percent Complete
  • Remaining Duration = Duration – Actual Duration.

If you type a value in the Percent Complete field in a summary task, Project Plan 365 automatically distributes the Percent Complete for subtasks. The distribution tries to add Actual Duration equally for each subtask which is scheduled as working starting from the Project Start Date.

For more information, please check our Percent Complete online help article.

How does the Project Plan 365 Scheduling Engine work?
Question Link
Answer

The Project Plan 365 Scheduling engine works as described below:

  1. First Step: Create a graph where nodes are tasks and edges are precedence relations between tasks and do a topological sort to get the order in which we should process the tasks so we calculate early start and early finish dates.
  2. Second Step: Create another graph for successors of tasks and calculate the late start and the late finish dates so we can calculate the real start and finish date of tasks and slack and we can obtain the project durationfinish date and critical path with better accuracy.
  3. Third Step: Compute other task fields like costwork and make sure that resource assignments are calculated correctly.
How can I know the "Planned Percentage Complete" of my project?
Question Link
Answer
Unfortunately, we don’t have a way to do this in Project Plan 365 because we don’t support formulas.
How can I change % complete to multiple tasks?
Question Link
Answer
We are sorry, but at this point our application you can't change the % complete for multiple tasks at the same time.
How to add new tasks and add them to the baseline without updating baseline information for the previous tasks which are already tracked?
Question Link
Answer

To set a Baseline for selected tasks, first select the tasks (using the Shift or Ctrl keys) then go to Project – Set Baseline. In the Set Baseline dialog select “Selected tasks” and click the “OK” button. This way the Baseline for the selected tasks will be set. The Baseline will be set when you Save your project.

How do I set a Baseline for selected tasks?
Question Link
Answer
To set a Baseline for selected tasks, first select the tasks (using the Shift or Ctrl keys) then go to Project – Set Baseline. In the Set Baseline dialog select “Selected tasks” and click the “OK” button. This way the Baseline for the selected tasks will be set. The Baseline will be set when you Save your project.
How Set Baseline works in a MPP file?
Question Link
Answer

To set a Baseline for the entire project click Project – Set Baseline. In the Set Baseline dialog select “Entire project” and click the “OK” button. This way the Baseline for the Entire Project will be set. The Baseline will be set when you Save your project.

Is there an option to set work contour for my project?

Question Link
Answer
We are sorry but, at this point, the "Work Contour" field is not editable in our application.
How to remove slack?
Question Link
Answer
To remove the Slack Time for a task, select the task, go to Task menu - Task Information - Predecessors tab and in the Lag time grid type 0 days.
What does the yellow diamond icon mean?
Question Link
Answer
The yellow diamond icon from the Indicators field shows the tasks that are overallocated.
Is it possible to store our subprojects in SharePoint?
Question Link
Answer
Is it possible to store our subprojects in SharePoint?
What subscription do I need to have to use the Resource Leveling feature?
Question Link
Answer
You must have a Business Subscription to use the "Resource Leveling" feature.
How can I manually resolve the overallocations?
Question Link
Answer
If you don’t want to level, you can try other ways to resolve overallocations.- Replace one resource with another who is available to work at that time.- Replace more skilled resources on critical tasks early in the project. A more skilled resource is likely to get the same job done in less time.- Change a task link so that some tasks start at the same time.- Spread the workload out by Increase the duration of tasks with overallocated resources.- Reduce workload by reducing the amount of work required for completing the task.- Change the working hours of resources to shorten the duration of tasks.- Reduce the duration of tasks, especially critical tasks that directly impact the project end date.- Check that resources are not working during non-working time. If a resource is working during non-working hours, Project will show them as overallocated.
Does Project Plan 365 resolve the overallocation for resources assigned to summary tasks?
Question Link
Answer
Project Plan 365 cannot resolve the overallocation for resources assigned to summary tasks.
Does Project Plan 365 resolve the overallocation of a resource assigned 200% to a task?
Question Link
Answer
No. Project Plan 365 does not change neither the duration nor work of the tasks as part of the resource leveling method.
Does Project Plan 365 consider the deadline when performing resource leveling?
Question Link
Answer
Project Plan 365 does not take care of deadlines when performing resource leveling
Can I level the tasks with %Complete grater than 0%?
Question Link
Answer
Project Plan 365 can fix overallocation only on tasks with % Complete set to 0%.
When to use the “Clear Leveling” option?
Question Link
Answer
Use the “Clear Leveling” option to undo the effects of the previous leveling.
How to clear resource leveling?
Question Link
Answer
To clear the leveling go to “Team” tab and click the “Clear Leveling” button. You can either clear the leveling for the entire project or just for the selected tasks.
How to level a task from the contextual menu?
Question Link
Answer
Select the task that you want to level, right click on it, and from the contextual menu chose the “Level Task” option. A summary of how Project Plan 365 fixed the overallocation will be displayed. Click the “OK” button for the changes to be applied.
How to level only the selected tasks?
Question Link
Answer
To level only the selected tasks, go to “Team” menu and click the “Level All” button. In the “Resource Leveling” dialog, the “Selected tasks” option and click the “OK” button. A summary of how Project Plan 365 fixed the overallocation will be displayed. Click the “OK” button for the changes to be applied.
How to level the entire project?
Question Link
Answer
To level the entire project, go to “Team” menu and click the “Level All” button. In the “Resource Leveling” dialog, the “Entire Project” option and click the “OK” button. A summary of how Project Plan 365 fixed the overallocation will be displayed. Click the “OK” button for the changes to be applied.
How to level the tasks of certain resources?
Question Link
Answer
To level tasks for certain resources, go to “Team” menu and click the “Level Resource” button. In the “Level Resources” dialog, select the resources for which you want to level tasks and click the “OK” button. A summary of how Project Plan 365 fixed the overallocation will be displayed. Click the “OK” button for the changes to be applied.
How to insert the Leveling Delay column?
Question Link
Answer
To insert the Leveling Delay column, right click on the column before which you want to insert it, and from the contextual menu choose the “Insert column…” option. Select “Leveling Delay” for the “Filed name” and click the “OK” button.
When should I use the Leveling Delay field?
Question Link
Answer
Add the Leveling Delay field to a task view if you want to examine the delays to tasks caused by resource leveling.