Is the "Assignment Owner" field editable?
Question Link
Answer
We are sorry, but the Assignment Owner field isn't editable in our application at this point.
How to access Project Plan 365 Portal page?
Question Link
Answer
Please click on the following link to access our Online Portal page: https://www.projectplan365.com/ups/Account/SignIn
How to plan expenses related to the purchase of equipment and materials needed to implement projects?
Question Link
Answer
For expenses related to the purchase of equipment (fixed cost), in Resource Sheet view you can add a resource of type cost. Then, you can assign that resource to a specific task in Task Information dialog under Team tab.
How can I plan and control equipment orders and deliveries (logistics activities) in the project?
Question Link
Answer
For material resources, in Resource Sheet you can add a resource of type material. Insert the material label and the Std. Rate. In Gantt Chart view or in Task information dialog you can specify the units for that specific material.
How can I see the resources grouped by resource type at a specific date in the project?
Question Link
Answer
We are sorry, but at this point our application doesn't allow to see the resources grouped by resource type at a specific date.
How to rename a resource?
Question Link
Answer
In order to rename a resource, go to the Resource Sheet view and double click on the desired resource to open the Resource Information dialog. In the Resource Name field, type the new name of the resource and click "OK" in the dialog for the changes to take effect.
Can I add the same resource in two different teams?
Question Link
Answer
With our current functionality a user’s email address cannot be assigned to two different teams.
How do I change the role for a team member from Read-Only to Editor?
Question Link
Answer

To change the role for a team member from Read-Only to Editor, Sign In in our Project 365 Online Portal and in Team Members page change the role for the desired team member. Note: 
1. By default, the owner of the organization has the Editor role.
2. If you already purchased a subscription, please know that you need to purchase a subscription for each Editor team member.
3. You can add as many read-only team members as you need for free.

Where can I find resource ribbon?
Question Link
Answer
The "Resource" menu was renamed and now you can find it as "Team" menu.
Where is Team menu?
Question Link
Answer
The menu "Team" can be found inside our application right next to the "Task" menu in the ribbon.
How do I set my max units to decimal?
Question Link
Answer
We are sorry, but at this point, the Max Units are only displayed in percent.
How do I assign multiple pay rates for a resource?
Question Link
Answer
We are sorry, but you cannot add multiple pay rates for a resource.
When/How a Team Member become a Resource and viceversa?
Question Link
Answer
When Team Member ‘John Smith’ is assigned to Task ABC in Project123 it becomes a local Resource to the project.

When local project Resource Mary Doe is added to the Organization XYZ it will become a Team Member and will be available to all projects in the organization.
When and why use Team Members or Resources in your project?
Question Link
Answer
You want to use Team Members any time you have shared people resources working in more than one project at the time so you can track their availability and avoid over allocations or under utilization.

You want to use local project Resources that are not Team Members only for material or equipment type resources.
What is a Resource?
Question Link
Answer
A resource is a person, equipment or materials that belongs to a project. Resources are defined and maintained at the project level.
What is a Team Member?
Question Link
Answer
A team member is a person that belongs to an organization - team members are assigned at the organization level and can be shared across multiple projects.
How do I add notes to a resource?
Question Link
Answer

There are 3 ways to add a note to a resource:
1. In Resource Sheet view click on the desired resource and go to Team – Notes.
2. Double click on ID cell associated with the desired resource in Resource Sheet view.
3. Insert the Notes field inside your table.

Where can I set Initials for my resource?
Question Link
Answer

​To set Initials for your resource click on the desired resource - Team menu tab - Information - General - Initials.

Can I set for my resource a code?
Question Link
Answer

​To set a code for your resource click on the desired resource - Team menu tab - Information - General - Code.​​

Where can I see the date when the pay rate takes effect for a resource?
Question Link
Answer

Information regarding resource's rates, including the standard rate, overtime rate, any per-use cost, and the date when the pay rate takes effect can be found by clicking the desired resource - Team menu - Information - Cost.

How do I use Resource Information?
Question Link
Answer

In order to open Resource Information dialog, go on Resource Sheet view select a resource then go on Team menu – Information or double click on resource name cell or right-click the resource and select Resource Information.

How do I add the team members into my plans? 
Question Link
Answer

To add Team Members into the current project, select a task and go to menu Team – Assign -  Team Member. It will open the Assign Team Members to This Task dialog, which lets you select who do you want to add to the current project. Once you click Assign, all the selected Team Members are added as Work Resources into the current project.  

You can also add team members from Gantt Chart view, using the Resource Names column.

When you open the Resource Names drop-down menu, you will get a list of all resources in your project and the Team Members (marked with an icon). Note that all the Team Members are visible in this list (added or not). Selecting any Team Member in this list will add it to the current project (only once). If you want to add a new Team Member, click Add Team Member button. 

Another option to add team members in your project is to use the Resource Sheet view. 

The Resource Name editing control provides a list of not added Team Members and the “Add Team Member” button. If there are no Team Members to suggest, the button alone is displayed.

Is it possible to insert more than one resource at a time?
Question Link
Answer

To insert multiple resources, select multiple consecutive rows using either CTRL or SHIFT keys on your keyboard and then press on Insert key or use the New Resource option from the contextual menu to insert multiple resources at a time. These resources will be positioned above the selected rows in the resources list. The number of newly inserted resources will be equal to the number of selected rows.​

How can I delete a resource?
Question Link
Answer

To delete a resource, on the View menu click Resource Sheet – select the resource’s name or select the row that corresponds to the resource – press the Delete key or use the Delete option under the Team tab or right click on the resource’s ID and select Delete Resource.

How can I delete multiple resources?
Question Link
Answer

To delete multiple resources, select multiple consecutive rows using either CTRL or SHIFT keys on your keyboard and then click on Delete option from the Team menu, or press on Delete key or use the Delete Resource option from the contextual menu to delete multiple resources at a time. The IDs of the remaining resources will be automatically renumbered.