How do I import the project into Primavera P6?
Question Link
Answer
You can export the project as XML file by going to menu File-Export-Export to XML and then import it in Primavera P6.
How do I change the color of the text inside the Gantt bars?
Question Link
Answer
To change the color of the text inside the Gantt bars, please go to menu Format – Text Styles and select Bar Text Inside then make the desired changes and click OK.
How do I add the Task Name inside the Bar in the Gantt Chart view?
Question Link
Answer
To add the Task Name inside the bar in Gantt Chart, go to the Format tab, click Bar Styles- select the type of Gantt bar – click Text tab – on the Inside field select Name – click OK.
Are the read-only team members able to open files from Drive 365?
Question Link
Answer
Any read-only team member can open and view the files stored in Drive 365 cloud.
Why the start of the tasks appears as 9:00 AM even though project schedule is set to start at 8:00?
Question Link
Answer
You need to set the working hours in both Options dialog under Advanced tab and in Change Working Time dialog (menu Project-Change Working Time) for each day.
How do I delete a subproject in a master project?
Question Link
Answer
To delete a subproject, select the summary project row, go to the Task menu and click on the "Delete" button.
The invited team members did not receive an invitation email.
Question Link
Answer
Please check the Spam folder and make sure that our domain name projectplan365.com is on your safe list. If you problem is not solved, please submit a ticket on our Support Team.
How can I open the application without the two "Add Individual Team Members" dialogs coming up every time?
Question Link
Answer
If you don't want the "Add Individual Team Members" dialogs to show up every time you open the application, please check the "Don't show this dialog again" checkbox inside the dialog.
How do I find the Print option on iPad?
Question Link
Answer
In order to find the Print option on iPad, go to the File menu - Print and select the "Print" option.
How do I export a dashboard project?
Question Link
Answer

In order to export your dashboard, go to menu File - Export - Export Dashboard.

How do I open a dashboard file?
Question Link
Answer

To open an existing Dashboard file click the Report Tab – Dashboard – Open – Select the dashboard file and make sure it is in XML format and click Open.The “Dashboard” option can also be found in File menuHome tabDashboard.

What happens if I delete the log file?
Question Link
Answer
If you delete the log file from your computer, a new .txt file will be created automatically when making actions in the application, only if the “Enable Local Logs” checkbox is checked inside the “Options” dialog.
What are the information that are logged in the .txt file?
Question Link
Answer
The following information are being logged:
  • Timestamp of event (user’s time)
  • Session Started indicator
  • Application Version
  • Application Language
  • App Events (Opened dialogs, Clicked buttons, etc.)
  • User Activity Events (Active User Email, Edit actions, Change view, etc.)
  • Errors
  • About Information
How to change the location of the log file?
Question Link
Answer
You can change the location where the text file is saved by going to the File menu – Options dialog, select “Usage Data” tab, check the “Enable Local Logs” checkbox (if not enabled) and type the full path to the file or click on the “Browse” button, select the new location, type the name of the .txt file and press “Save”. After that, click “OK” button inside the “Options” dialog for the changes to take effect. Events will be logged in the new file.
Where is the text file saved?
Question Link
Answer
The default location for the logs file is‘%AppData%/Project Plan 365/LocalLogs.txt’. This can be changed at any time.

Note: Depending on app usage, the logs file may get pretty big.
How to disable “Local Logs”?
Question Link
Answer
In order to disable “Local Logs”, go to the File menu – Options, select “Usage Data” tab and from Troubleshooting section, uncheck “Enable Local Logs” checkbox. After that, click “OK” in the “Options” dialog for the changes to take effect.
How to enable “Local Logs”?
Question Link
Answer
Local Logs are disabled by default but they can be enabled at any time. In order to enable “Local Logs”, go to the File menu – Options, select “Usage Data” tab and from Troubleshooting section, check the “Enable Local Logs” checkbox. After that click “OK” in the “Options” dialog for the changes to take effect. Events will start to be logged right away in the “Local Logs File”.
What does the “Local Logs” functionality do?
Question Link
Answer
Local Logs is a system which logs in-app events that are stored locally in a text file which can be used in order to identify the steps for reproducing an error.
Is there a way to implement a Window Tab where we can circle between opened Projects on Mac?
Question Link
Answer
To find all the opened projects on Mac, please right-click on the Project Plan 365 icon and then click on Show All Windows button.
How do I delete sprints?
Question Link
Answer
We are sorry but the delete sprints option isn't available in our application at this point.
Can I assign resources to a task via the Task Form or it is viewing mode only?
Question Link
Answer
The Task Form view is read-only at this point.
I created a calendar for a project , can I use it in another project?
Question Link
Answer
With our Business Subscription, you can save your .MPP file with the desired calendar as an organization template.
How can I extract a WBS chart or diagram corresponding to the project tasks?
Question Link
Answer

You can see the Network Diagram by going to menu View-Network Diagram or you can select the view in the right bar.

To export the Network Diagram, please go to menu View-Network Diagram then go to menu File-Print.

To see the WBS you can insert the WBS column by going to menu Format-Insert columns. Select WBS and click OK.

Another way to see the WBS is to add the outline number in the Task Name column by going to menu File-Options and in Advanced tab select “Show outline number”.

When modifying baseline work field into the variance table does not sum to summary task. All summary totals must be recomputed manually.
Question Link
Answer

The changes made to the baseline fields do not cause the project to be recalculated.

After you set a baseline, you can still edit baseline values. However, edited baseline values do not cause any recalculation of baseline work fields.

The best approach to using the Baseline Work field, would be to make the desired changes to the Work field then set a baseline.

How do I indicate the current date of the project?
Question Link
Answer
In order to see the current date of your project, go to the Project menu and select "Project Information" option.